NPS 12 Schedule 5 Pipe
12.750 in (323.8 mm) outside diameter on a 0.156 in (4.0 mm) wall, giving a 12.438 in (315.9 mm) bore and 20.98 lb/ft (31.23 kg/m) empty. ASME B36.10M.
- Nominal size
- NPS 12 (DN 300)
- Schedule
- Schedule 5
- Outside diameter
- 12.750 in (323.8 mm)
- Wall thickness
- 0.156 in (4.0 mm)
- Inside diameter
- 12.438 in (315.9 mm)
- Weight, empty
- 20.98 lb/ft (31.23 kg/m)
- Weight, water filled
- 73.66 lb/ft (109.62 kg/m)
- Flow area
- 121.504 in² (78390 mm²)
No other designation in NPS 12 shares this wall thickness, so Schedule 5 is unambiguous in this size.
Every schedule in NPS 12
Dimensions are given in inches, with the millimetre equivalent beneath in grey.
| Schedule | Wall thickness | Inside diameter | Weight, empty | Water (US gal/ft) |
|---|---|---|---|---|
| Sch 5 this page | 0.1563.96 mm | 12.438315.93 mm | 20.9831.23 kg/m | 6.312 |
| Sch 10 | 0.1804.57 mm | 12.390314.71 mm | 24.1735.96 kg/m | 6.263 |
| Sch 20 | 0.2506.35 mm | 12.250311.15 mm | 33.3849.67 kg/m | 6.123 |
| Sch 30 | 0.3308.38 mm | 12.090307.09 mm | 43.7765.14 kg/m | 5.964 |
| Sch 40 | 0.40610.31 mm | 11.938303.23 mm | 53.5379.65 kg/m | 5.815 |
| STD | 0.3759.52 mm | 12.000304.80 mm | 49.5673.76 kg/m | 5.875 |
| Sch 60 | 0.56214.27 mm | 11.626295.30 mm | 73.16108.87 kg/m | 5.515 |
| Sch 80 | 0.68817.48 mm | 11.374288.90 mm | 88.63131.90 kg/m | 5.278 |
| XS | 0.50012.70 mm | 11.750298.45 mm | 65.4297.35 kg/m | 5.633 |
| Sch 100 | 0.84421.44 mm | 11.062280.97 mm | 107.32159.71 kg/m | 4.993 |
| Sch 120 | 1.00025.40 mm | 10.750273.05 mm | 125.49186.75 kg/m | 4.715 |
| Sch 140 | 1.12528.57 mm | 10.500266.70 mm | 139.68207.86 kg/m | 4.498 |
| Sch 160 | 1.31233.32 mm | 10.126257.20 mm | 160.27238.51 kg/m | 4.183 |
| XXS | 1.00025.40 mm | 10.750273.05 mm | 125.49186.75 kg/m | 4.715 |
Weight is plain-end carbon steel, w = 10.6802 × t × (OD − t) lb/ft.
Flanges for NPS 12 pipe
Flange dimensions are set by NPS and pressure class, not by schedule, so every flange below fits this pipe. The exception is the weld neck: its bore is machined to the pipe it is welded to, which for Schedule 5 means 12.438 in (315.9 mm). Order the flange to the schedule or the bores will not line up at the weld.
| Class | Flange OD | Thickness | Bolt circle | Bolting |
|---|---|---|---|---|
| Class 150 | 19.00482.60 mm | 1.2531.75 mm | 17.00431.80 mm | 12 × 7/8 in |
| Class 300 | 20.50520.70 mm | 2.0050.80 mm | 17.75450.85 mm | 16 × 1 1/8 in |
| Class 400 | 20.50520.70 mm | 2.2557.15 mm | 17.75450.85 mm | 16 × 1 1/4 in |
| Class 600 | 22.00558.80 mm | 2.6266.55 mm | 19.25488.95 mm | 20 × 1 1/4 in |
| Class 900 | 24.00609.60 mm | 3.1279.25 mm | 21.00533.40 mm | 20 × 1 3/8 in |
| Class 1500 | 26.50673.10 mm | 4.88123.95 mm | 22.50571.50 mm | 16 × 2 in |
| Class 2500 | 30.00762.00 mm | 7.25184.15 mm | 24.38619.25 mm | 12 × 2 3/4 in |
Fittings for NPS 12 pipe
ASME B16.9 dimensions come from NPS alone, so these figures hold for Schedule 5 exactly as they do for every other schedule in the size. Only the wall thickness has to be ordered to match.
| Fitting | Dimension | NPS 12 |
|---|---|---|
| 90° Long Radius Elbow | Centre-to-end A | 18.00457.20 mm |
| 90° Short Radius Elbow | Centre-to-end A | 12.00304.80 mm |
| 45° Long Radius Elbow | Centre-to-end B | 7.50190.50 mm |
| Straight Tee | Centre-to-end C and M | 10.00254.00 mm |
| Reducing Tee | Run centre-to-end C | 10.00254.00 mm |
| Concentric Reducer | End-to-end H | 8.00203.20 mm |
| Eccentric Reducer | End-to-end H | 8.00203.20 mm |
| Cap | Length E | 6.00152.40 mm |
Common questions
What is the inside diameter of NPS 12 schedule 5 pipe?
12.438 in (315.9 mm). The outside diameter is fixed at 12.750 in (323.8 mm) by ASME B36.10M, and the 0.156 in (4.0 mm) wall takes 0.312 in off it — 0.156 in from each side — leaving that bore.
How much does NPS 12 schedule 5 pipe weigh?
20.98 lb/ft (31.23 kg/m) empty, as plain-end carbon steel. Full of water it comes to 73.66 lb/ft (109.62 kg/m), because the bore holds 6.312 US gallons per foot. One short ton of this pipe is about 95 ft.
Does NPS 12 schedule 5 pipe use special flanges or fittings?
No. Flanges and buttweld fittings are dimensioned from NPS, so NPS 12 hardware fits this pipe in any schedule. The one thing that does follow the schedule is the bore of a weld neck flange or a fitting end prep, which has to be 12.438 in (315.9 mm) to match.