Pipe Sizing by Flow Rate and Velocity

How to get from a flow rate to a nominal pipe size: the continuity equation, the velocity limits that apply to each service, and a full Schedule 40 capacity table.

Sizing basis
Velocity, then pressure drop
Typical liquid target
6 – 8 ft/s
Pump suction target
2 – 4 ft/s
Capacity formula
Q = 3.117 × A × v

Short answer. Pipe is sized by picking a target velocity for the service, converting it to a required flow area, and then rounding up to the next standard NPS. Pressure drop is checked afterwards and governs on long runs. For ordinary pumped liquid, 6 to 8 ft/s is the usual starting point; pump suction lines are sized much lower, at 2 to 4 ft/s, to protect NPSH.

The sizing equation

Flow rate, area and velocity are related by continuity. In the units the work is actually done in:

Q (US gpm) = 3.117 × A (in²) × v (ft/s)
A (in²) = Q / (3.117 × v)  ·  v (ft/s) = Q / (3.117 × A)

The constant is not magic: it converts in²·ft/s to US gallons per minute — multiply by 12 for inches per second, by 60 for minutes, and divide by 231 cubic inches per gallon.

Worked example

Size a line for 400 gpm of cooling water on a pump discharge, target velocity 8 ft/s.

  1. Required area: A = 400 / (3.117 × 8) = 16.04 in²
  2. Required bore: d = √(4A/π) = 4.52 in
  3. The smallest Schedule 40 size meeting that is NPS 5, bore 5.047 in (128.2 mm), area 20.01 in².
  4. Actual velocity at 400 gpm in NPS 5 Sch 40: v = 400 / (3.117 × 20.01) = 6.4 ft/s — below the target, because the standard size is larger than the exact requirement.

Note that NPS 5 is one of the sizes many piping specifications exclude from their standard size list. Where that applies, the next permitted size is taken instead — which is the usual reason a line ends up larger than the calculation strictly requires.

Always round up to the next standard size. Rounding down raises velocity, and pressure drop rises with roughly the square of velocity — so a half-size saving on pipe can cost far more in pump power over the life of the line.

Design velocity by service

Customary design velocity ranges by service.
ServiceTypical velocityWhy
Pump suction, liquid2 – 4 ft/sKept low to protect NPSH available. High suction velocity is a leading cause of cavitation.
Pump discharge, liquid6 – 12 ft/sThe usual economic range for water and light hydrocarbons.
General process liquid4 – 8 ft/sBalances pumping cost against pipe cost.
Gravity drain and flow lines2 – 5 ft/sLimited by available head, and must stay self-venting.
Slurry4 – 8 ft/sAbove the settling velocity to keep solids suspended, below the erosion limit for the material.
Saturated steam80 – 150 ft/sHigher velocities are tolerable but noise and erosion rise sharply.
Superheated steam100 – 200 ft/sDry steam is less erosive, so higher velocity is acceptable.
Compressed air and gas30 – 60 ft/sSet by pressure drop over the run rather than by erosion.
Pump suction, boiling liquid1 – 3 ft/sAnything at its bubble point needs the lowest suction velocity you can afford.

These are common engineering practice, not code requirements. Project specifications and the fluid's own erosion behaviour override them.

Flow capacity, Schedule 40

Capacity at four common design velocities for every Schedule 40 size through NPS 24, computed from the published bore.

Dimensions are given in inches, with the millimetre equivalent beneath in grey.

Schedule 40 flow capacity in US gpm at four design velocities.
NPSBore (Sch 40)Flow area3 ft/s6 ft/s8 ft/s10 ft/sUS gal per ft
NPS 1/80.2696.83 mm0.057 in²11120.003
NPS 1/40.3649.25 mm0.104 in²12330.005
NPS 3/80.49312.52 mm0.191 in²24560.010
NPS 1/20.62215.80 mm0.304 in²36890.016
NPS 3/40.82420.93 mm0.533 in²51013170.028
NPS 11.04926.64 mm0.864 in²81622270.045
NPS 1 1/41.38035.05 mm1.496 in²142837470.078
NPS 1 1/21.61040.89 mm2.036 in²193851630.106
NPS 22.06752.50 mm3.356 in²3163841050.174
NPS 2 1/22.46962.71 mm4.788 in²45901191490.249
NPS 33.06877.93 mm7.393 in²691381842300.384
NPS 3 1/23.54890.12 mm9.887 in²921852473080.514
NPS 44.026102.26 mm12.730 in²1192383173970.661
NPS 4 1/24.506114.45 mm15.947 in²1492983984970.828
NPS 55.047128.19 mm20.006 in²1873744996241.039
NPS 66.065154.05 mm28.890 in²2705407209001.501
NPS 77.023178.38 mm38.738 in²3627249661,2072.012
NPS 87.981202.72 mm50.027 in²4689361,2471,5592.599
NPS 98.941227.10 mm62.786 in²5871,1741,5661,9573.262
NPS 1010.020254.51 mm78.854 in²7371,4751,9662,4584.096
NPS 1111.000279.40 mm95.033 in²8891,7772,3702,9624.937
NPS 1211.938303.23 mm111.932 in²1,0472,0932,7913,4895.815
NPS 1413.124333.35 mm135.276 in²1,2652,5303,3734,2167.027
NPS 1615.000381.00 mm176.715 in²1,6523,3054,4065,5089.180
NPS 1816.876428.65 mm223.681 in²2,0924,1835,5776,97211.620
NPS 2018.812477.82 mm277.946 in²2,5995,1986,9318,66314.439
NPS 2422.624574.65 mm402.002 in²3,7597,51810,02412,53020.883

Computed from the ASME B36.10M bore. For another schedule, scale by the ratio of flow areas — see the size pages for each schedule's bore.

Erosional velocity

For two-phase and gas service, API RP 14E gives an erosional velocity limit that is widely used as a check:

Ve = C / √ρ  ·  ρ in lb/ft³, Ve in ft/s

C is commonly taken as 100 for continuous service in carbon steel and 125 for intermittent service, with higher values for corrosion-resistant alloys and clean, non-corrosive fluids. The correlation is empirical and has been criticised as conservative for clean service and unconservative where sand is present — treat it as a screening check, not a design basis.

When pressure drop governs instead

Velocity sizing works because on a short line the velocity limit is reached before the pressure drop budget is. On long runs the reverse is true, and the line must be sized on the Darcy-Weisbach loss against the available head. As a rule of thumb, anything over a few hundred feet should be checked on pressure drop, and anything feeding a pump or a control valve should be checked regardless of length.

Common questions

What velocity should I size a water line for?

6 to 8 ft/s for a pumped discharge line is the usual starting point. Pump suction lines are sized much lower — 2 to 4 ft/s — because suction velocity eats into the NPSH available.

How do I convert gpm to pipe size?

Divide the flow by 3.117 times the target velocity to get the required area in square inches, convert that to a diameter, and round up to the next standard NPS. The capacity table above does the same thing by lookup.

How many gallons per minute can a 4 inch pipe carry?

NPS 4 Schedule 40 has a bore of 4.026 in and a flow area of 12.73 in², giving about 238 gpm at 6 ft/s and 397 gpm at 10 ft/s. The practical answer depends entirely on the velocity you are willing to run.

Does schedule affect flow capacity?

Yes, significantly. A heavier schedule has the same outside diameter but a smaller bore, so it carries less at the same velocity. Schedule 80 gives up roughly 15% of the Schedule 40 flow area.

Why size pump suction lines larger than discharge lines?

To protect the net positive suction head available. Friction loss and velocity head on the suction side subtract directly from NPSHa, and losing it causes cavitation.